±¬×ߺÚÁÏ

Pour les actualités en français, voir la page News in French.

First plant components now in place

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ±¬×ߺÚÁÏ installation have all reached the ±¬×ߺÚÁÏ site. The first one had been the first Highly Exceptional Load to travel along the ±¬×ߺÚÁÏ Itinerary in January; three more were delivered on 21 May in a single transport operation.
 
A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ±¬×ߺÚÁÏ plant.
 
The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.
 
The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "±¬×ߺÚÁÏ could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ±¬×ߺÚÁÏ Electrical Power Distribution section leader Joël Hourtoule.
 
The second pair of transformers will be installed in the coming weeks.
 
View a slide show of the convoy and transformer installation below.